Constructor Group

Constructor Group

The front of the existing warehouse, with Space just about to get started and stuck in!

On site

Space are on site.

Cabins

Warehouse staff cabins are installed.

Cabins

Site cabins are installed.

De-IT

Staff have packed up and Space are in to de-IT and move them to temporary office.

Warehouse

The tornado unit in the warehouse is moved by Constructor.

Empty Space

Furniture is removed and demolition begins!

Power

Power and lighting isolations and ceilings stripped out and wall linings removed.

Ceiling

First floor ceiling removed - time to begin carefully removing the cabling mess left behind.

Segregation

Segregation installed between warehouse and site areas to help control the dust.

Asbestos

Asbestos removal is underway, site areas are restricted.

Drainage

Dig to the front for new drainage feeds.

Room partitions

1st floor toilets/ kitchen / store room partitions stripped out.

Open Space

1st floor looking bare.

Cabling

The old cabling is being stripped out.

Clearing Out

Lots of rubbish to segregate and clear out.

Progress

1st floor demo progress.

Asbestos Works

Main entrance area sealed for the duration of the asbestos works to keep everyone safe.

Demolition Crew

Area by front roller-shutter cleared by the demolition crew.

Boiler Romoved

Old boiler removed.

Drainage Connection

Front trench is filled back in with drainage connections ready to be ran into building in new locations and temporary water feed lagged.

Mezzanine floor

Mezzanine floor cleared ready to be removed.

Taking apart

Mezzanine floor cleared ready for the old water tank to be removed and then the whole floor itself can be taken apart.

Clean Up

Cleaned up area following asbestos removal.

New Concrete

New concrete base is poured to side of building for new AC condensers.

Concrete Base

Existing concrete base cleared ready for the bike rack.

Bare concrete

Old shower room floor cleared of all asbestos and returned to bare concrete.

Asbestos Skip

Big yellow asbestos skip filled already for the safe removal from site

Asbestos safely removed

Main corridor also returned to bare concrete and all asbestos safely removed.

Asbestos packers

Central block wall ready for Asbestos packers to be removed.

Fibre intake cupboard

Old fibre intake cupboard ready to remove once BT are complete.

Boards removed

Old board room moved.

Mezzanine Floor

Mezzanine floor removed to expose new demo area.

Warehouse

Old warehouse office fully stripped.

Demolition

Demolition nearly complete.

Bare Warehouse

Demolition complete and back to a bare warehouse.

Diamond Drilled

Concrete is diamond drilled ready for the piling teams Auger to drill out.

Diamond Drilled

Concrete is diamond drilled ready for the piling teams Auger to drill out.

Steel Piling

Steel piling encasements are delivered to site.

Steel Piling

Steel piling encasements are delivered to site.

Piling Rig Arrives

Piling Rig arrives on site ready to commence works.

Piling Rig Bores

Piling Rig bores a hole to make way for the piling encasements.

Thick Clay and Mud

The thick clay and mud are no match for the piling Rig!

Steel Encasement

Steel encasements being driven into the ground with ½ metric tonne pile.

DPM

DPM in place around piling cap ready for the concrete to be poured.

Steel Cage

Steel cage to be encased in concrete on the piling cap for reinforcement.

Fixing Points

Fixing points for first floor A.C units and containment being installed.

Cladding Stripped.

Old cladding is stripped off.

AC units

AC units and containment going up ready for the first floor.

Fireboards

Demo area fireboard and insulation going up.

Steel Beam

New steel beam is installed along the front perimeter for the new Mezz.

Cladding

Cladding finished on the front elevation.

Steel Works

Steel works fully installed ready for the mezzanine floor.

Brick Work

Brickwork to front elevation complete.

New Windows

New windows are created to break out area.

New Side Window

New side window is cut in and trimmed.

Side Windows

New side window and grill locations for are cut in.

Duct Works

New ductwork for fresh air is being installed.

New Pad Stones

New pad stones are cut in.

Doorway

New doorway and window opening to warehouse office are cut into block wall.

Pad Stones Ready For Mezzanine

New pad stones are in all ready for the Mezzanine to be installed.

PIR Insulation

PIR Insulation is being fitted to the front elevation.

Ductwork

Fresh air ductwork is first fixed high level.

Insulation

Insulation is nearly complete to the front elevation covering all beams and purlins.

Mezz

Mezzanine floor is being installed this photo shows the main steel beams and the joists that will hold up the floor.

Mezz

Steel plates welded into the web of the building steels for strength.

Roller Shutter

Old roller shutter has been removed to make way for the new one.

Mezz Floor

Mezz floor at the beginning of the weekend, purlins ready to go in.

Timber Deck

Timber deck beginning to be laid.

Purlins Fully Completed

Purlins fully installed on Saturday.

Roller Shutter

Roller shutter fully installed over the weekend, looking nice in the goosewing grey, a definite improvement on the old one!

Timber Deck

Timber deck filly laid in one bay ready to be fire lined.

Ready To Be Fire Lined

Timber deck filly laid in one bay ready to be fire lined.