Dyer & Butler Phase 2

Dyer & Butler

Take a look throughout our project timeline of phase 2 of our client Dyer & Butler!

Demolition

Strip out works have begun!

Strip Out

Strip out completed ground & 1st floor.

Site Set Up

Site has been set up!

Site Set Up

Site is up and running.

Brickwork

Existing brickwork / blockwork & lintels knocked through to create new opening & doorway.

Doorway

New lintel installed to ground floor doorway.

Partitions

Ground floor partitions being installed.

Stud Work

Stud work erected on 1st floor.

Floor Box

Floor box chase cut out & 1st floor fix electrical to 10P meeting room.

Lintel

1st floor lintel installed to new opening.

Partitions

Partitions insulation being installed on 1st floor.

Doors

Existing double doors removed in 1st floor corridor, new temporary separation installed.

Partitions

Boarding to 1st floor partitions.

Partitions

Partitions boards installed ready for decorating.

Partitions

New partitions complete.

Plastering

New openings ready for plastering.

Aluminium

Aluminium door frames installed.

T&J

Taping & Jointing works have begun.

Plastering

Plastering to new openings.

Openings

Existing openings now closed up.

Plastering

Plastering is complete on 1st floor & ground floor.

Decorations

Decorations to new partitions have begun!

Trunking

New skirting trunking for power and data being installed.

Ceiling Grid

New ceiling grid being installed.

Lighting Panels

New lighting panels installed to new offices.

Glazing Track

Glazing track has be installed.

Ceiling Grid

Ceiling grid installed and completed.

Ceiling

Ceiling tiles installed.

Ceiling

Ceiling tiles and lights installed in 1st floor corridor.

Timber Door Frames

Timber door frames installed on ground floor.

Power & Data

power and data installed to suit new layout.

Decorations

Decorations completed on 1st floor.