Matchtech

Matchtech Fareham

Take a look through our project timeline of the Matchtech office in Fareham!

Temporary Partitions

Temporary partitions to separate the 1st and 2nd phase.

Partitions

Temporary partitions to split second floor phase 1 and 2

Partitions

Temporary partitions are up to separate the second floor.

De-Gas

De-gas of existing condensers ready to strip out the first phase AC units.

Partitions

Partition and bulkhead created for new tea-point.

Partitions

Partitions created for Storewall.

Mechanical

Delivery of new AC cassettes and the old ones stripped out.

New Pipework

New pipework is ran for the new AC systems from ground floor compound to first and second floors.

New Pipework

New pipework is ran for the new AC systems from ground floor compound to first and second floors.

T&J

Taping and Jointing new partitions.

BC Box

New BC box installed for the new AC system on 2nd floor.

AC

New AC cassettes have been installed.

LED

New LED light panels being installed into grid.

Data

First fix data is underway.

Tea Point

Tea Point is being installed.

Tea Point

Tea Point is being installed.

Piping

Piping for the first phase AC units is installed from the BC box.

LED Panels

New LED panels are up.

Tea Point

Tea Point is installed, just waiting for the special order wall unit doors and quartz stone worktop.

Decorations

Decorations are underway.

Data

Data second fixed into new cab on 2nd floor, with fibre and copper links to ground floor comms room.

Data

Data second fixed into new cab on 2nd floor, with fibre and copper links to ground floor comms room.

Crane

The crane is here to lift out the old condensers and lift in the new.

AC

The second floor condensers are gone.

AC

New condensers are now in place!

Glazing Track

Black glazing track is installed for glass screen to tea-point and new round lights are installed.

Light

Let there be light!

WC

WC's basin is in!

Flooring

Carpet is down with power and data ready for the desk install.

T-Point

Worktop has been installed.

Desks

Desks have been installed!

Splashback

Splashback has been installed!

Office

First phase is ready to hand over.

TPoint

Tpoint for the first phase is done!

Desks

Desks and furniture are in!

Desks

Desks and furniture is in!

Demolition

Demo to gents toilet and opening made for extension.

Plastering

Plastering to toilets.

Plastering

Plastering to toilets and new opening.

Partitions

New partitions to extended toilets.

Tea Point

Existing teapoint stripped out.

Partitions

Extended toilet partitions out into the office space.

Pipework

Pipework runs for new AC cassettes.

AC

New AC cassettes and lights going in.

Tea Point

New doors fitted to the tea point wall units in the dark grey matte.

Office

New partitions to create office and meeting room.

Electrics

First fix electrics in partition for TV positions.

Floor

Floor to extended toilet is plied and primed ready for latex screed.

Partitions

Partition walls closed up.

Glazing

Glazing track and door frames installed.

Fan Units

New fan units installed for toilet extraction in plant room.

Ducting

Ducting work installed in male toilets for extraction system.

T&J

Tape & Jointing to new partitions.

Data Cables

Data cables been pulled into position in floor void.

T&J

T&J to New Partitions.

Lighting

New Lighting is on in phase 2

Decorations

Decorations are underway.

Toilet Wall

Toilet wall is lined out and 1st fix plumbing complete for new sinks.

Plumbing

1st fix plumbing complete in the cleaners cupboard ready for lagging.

Toilets

Extended toilets waste and feeds 1st fixed.

Glazing Track

Glazing Track is fully complete ready for glass survey.

Glazing Track

Existing office glazing track is sprayed black to match the new stuff.

Storage

Storage unit & worktop installed to reprographics area.

OSB Wall

OSB Wall around comms room is installed ready for decoration.

Ceiling

New ceiling installed in toilets with new lighting and extraction.

OSB Wall

The OSB wall is painted black.

Comms Cabinet

The comms cabinet is moving to its new housing.

Feature Wall

Grey feature wall to divide the new office and meeting room.

Flooring

New floor tiles installed in the gents toilets.

Ceilings

The ceilings are tied back in and waiting for final coats to the OSB wall.

Office

New office and meeting room.

Duct Panelling

The new duct paneling is being installed.

Decorations

A look down site with decorations nearly complete and nearly ready to start flooring.

Sinks

New trough sinks installed ready for wall tiling.

Cubicle

Duct panel and cubicle installed complete.

Cubicle

Duct panel and cubicle install complete.

Partitions

Glass partitions and doors installed to new office and meeting room.

Carpet

Carpet install is underway!

Carpet

Carpet install is underway!

Carpet

Carpet install is complete.

Carpet

Carpet install is complete.

Wall Tiling

Wall tiling complete and second fix plumbing underway to trough sinks.

Second Fix Plumbing

Second fix plumbing to the new toilets is in progress.

Second Fix Plumbing

Second fix plumbing to new toilets in progress.

Glass Boards

Glass boards are installed to phase 2.

Glass Boards

Glass boards are installed to Phase 2.

Doors

New white gloss laminate doors fitted to floor entrance and toilets.

Toilets

Toilets nearly complete, just in need of final clean and mastic.

Toilets

Toilets nearly complete, just in need of final clean and mastic.

Toilets

Toilets nearly complete, just in need of final clean and mastic.

Toilets

Toilets nearly complete, just in need of final clean and mastic.

Storewall

Storewall units are installed.

Desk Install

The desks have been installed.

Desks

The desks have been installed.

Desks

Desks have been installed.

Final Touches

Final clean and mastic to toilets now ready to use!

Manifestation

New manifestation to MD's office.

IT

Client has moved in the IT for staff relocation.

IT

Client has moved in the IT for staff relocations.

Handover

Handover of phase 2 and the 2nd floor.

Handover

Handover of phase 2 and the 2nd floor.

MD Office

MD's office is handed over.

MD Office

MD's office has been handed over.

Reprographics

Reprographics area.

Site Set Up

Ready for the next phase, 1st floor.

Demo

Demo underway in ladies toilet 1st floor.

Site Set Up

Slowly clearing the remainders of 1st floor clutter and setting up temporary lighting.

Partitions

Delivery of partitioning material for 1st floor.

Female Toilets

The opening has been made to extend the first floor female toilets, ready for plastering.

Toilets

The old toilet walls are plastered.

Toilet

Lining out to create the extended part of the toilet is underway.

Crane Lift

Crane lift for the new condensers for first floor AC system.

Reprographics

Lining out to the reprographics area wall.

Extended Toilets

Extended toilet walls are boarded up.

Tea Point

New Tea Point bulkhead and back wall created

Toilets

First fix ductwork to new ladies toilet.

Toilet Wall

Toilet wall lined out to conceal pipework underneath 'floating trough sink'.

Condensers

Out with the old and in with the new!

Data Cabling

Old data cabling being stripped out.

Tea Point

New teapoint extract is first fixed.

New Office

New meeting room and office are created and ready for boarding.

AC

New cassettes and light tiles are located into the ceiling, ready for pipework and connections.

T&J

Tape and jointing underway to new partitions.

Meeting Room

Jointing and first fix electrics in meeting room.

AC

New BC Controller for first floor AC system is installed and being piped up.

Extended Toilet

Jointing to the extended toilet.

Tea Point

First Fix electrics and plumbing installed to tea-point wall.

Plumbing

First fix plumbing to ladies toilet for new sinks.

Chasing

Chasing and first fix AV power in office wall.

Jointed

Reprographics area and comms wall jointed.

Data

First fix new data is underway

Flooring

Floor is plied and screeded in the extended ladies.

Ceiling Grid

New ceiling grid is installed in the ladies.

Tea Point

Tea-Point is delivered ready for install.

AC Pipework

AC pipework is nearly complete internally.

First Fix

First fix data and aerial to new tray in ceiling void.

Jointing

Jointing is complete all ready for decorations to begin.

Lighting

New lighting is on and the new cassettes are installed into the ceiling.