Matchtech

Matchtech Fareham

Take a look through our project timeline of the Matchtech office in Fareham!

Temporary Partitions

Temporary partitions to separate the 1st and 2nd phase.

Partitions

Temporary partitions to split second floor phase 1 and 2

Partitions

Temporary partitions are up to separate the second floor.

De-Gas

De-gas of existing condensers ready to strip out the first phase AC units.

Partitions

Partition and bulkhead created for new tea-point.

Partitions

Partitions created for Storewall.

Mechanical

Delivery of new AC cassettes and the old ones stripped out.

New Pipework

New pipework is ran for the new AC systems from ground floor compound to first and second floors.

New Pipework

New pipework is ran for the new AC systems from ground floor compound to first and second floors.

T&J

Taping and Jointing new partitions.

BC Box

New BC box installed for the new AC system on 2nd floor.

AC

New AC cassettes have been installed.

LED

New LED light panels being installed into grid.

Data

First fix data is underway.

Tea Point

Tea Point is being installed.

Tea Point

Tea Point is being installed.

Piping

Piping for the first phase AC units is installed from the BC box.

LED Panels

New LED panels are up.

Tea Point

Tea Point is installed, just waiting for the special order wall unit doors and quartz stone worktop.

Decorations

Decorations are underway.

Data

Data second fixed into new cab on 2nd floor, with fibre and copper links to ground floor comms room.

Data

Data second fixed into new cab on 2nd floor, with fibre and copper links to ground floor comms room.

Crane

The crane is here to lift out the old condensers and lift in the new.

AC

The second floor condensers are gone.

AC

New condensers are now in place!

Glazing Track

Black glazing track is installed for glass screen to tea-point and new round lights are installed.

Light

Let there be light!

WC

WC's basin is in!

Flooring

Carpet is down with power and data ready for the desk install.

T-Point

Worktop has been installed.

Desks

Desks have been installed!

Splashback

Splashback has been installed!

Office

First phase is ready to hand over.

TPoint

Tpoint for the first phase is done!

Desks

Desks and furniture are in!

Desks

Desks and furniture is in!

Demolition

Demo to gents toilet and opening made for extension.

Plastering

Plastering to toilets.

Plastering

Plastering to toilets and new opening.

Partitions

New partitions to extended toilets.

Tea Point

Existing teapoint stripped out.

Partitions

Extended toilet partitions out into the office space.

Pipework

Pipework runs for new AC cassettes.

AC

New AC cassettes and lights going in.

Tea Point

New doors fitted to the tea point wall units in the dark grey matte.

Office

New partitions to create office and meeting room.

Electrics

First fix electrics in partition for TV positions.

Floor

Floor to extended toilet is plied and primed ready for latex screed.

Partitions

Partition walls closed up.

Glazing

Glazing track and door frames installed.

Fan Units

New fan units installed for toilet extraction in plant room.

Ducting

Ducting work installed in male toilets for extraction system.

T&J

Tape & Jointing to new partitions.

Data Cables

Data cables been pulled into position in floor void.

T&J

T&J to New Partitions.

Lighting

New Lighting is on in phase 2

Decorations

Decorations are underway.

Toilet Wall

Toilet wall is lined out and 1st fix plumbing complete for new sinks.

Plumbing

1st fix plumbing complete in the cleaners cupboard ready for lagging.

Toilets

Extended toilets waste and feeds 1st fixed.

Glazing Track

Glazing Track is fully complete ready for glass survey.

Glazing Track

Existing office glazing track is sprayed black to match the new stuff.

Storage

Storage unit & worktop installed to reprographics area.

OSB Wall

OSB Wall around comms room is installed ready for decoration.

Ceiling

New ceiling installed in toilets with new lighting and extraction.

OSB Wall

The OSB wall is painted black.

Comms Cabinet

The comms cabinet is moving to its new housing.

Feature Wall

Grey feature wall to divide the new office and meeting room.

Flooring

New floor tiles installed in the gents toilets.

Ceilings

The ceilings are tied back in and waiting for final coats to the OSB wall.

Office

New office and meeting room.

Duct Panelling

The new duct paneling is being installed.

Decorations

A look down site with decorations nearly complete and nearly ready to start flooring.

Sinks

New trough sinks installed ready for wall tiling.

Cubicle

Duct panel and cubicle installed complete.

Cubicle

Duct panel and cubicle install complete.

Partitions

Glass partitions and doors installed to new office and meeting room.

Carpet

Carpet install is underway!

Carpet

Carpet install is underway!

Carpet

Carpet install is complete.

Carpet

Carpet install is complete.

Wall Tiling

Wall tiling complete and second fix plumbing underway to trough sinks.

Second Fix Plumbing

Second fix plumbing to the new toilets is in progress.

Second Fix Plumbing

Second fix plumbing to new toilets in progress.

Glass Boards

Glass boards are installed to phase 2.

Glass Boards

Glass boards are installed to Phase 2.

Doors

New white gloss laminate doors fitted to floor entrance and toilets.

Toilets

Toilets nearly complete, just in need of final clean and mastic.

Toilets

Toilets nearly complete, just in need of final clean and mastic.

Toilets

Toilets nearly complete, just in need of final clean and mastic.

Toilets

Toilets nearly complete, just in need of final clean and mastic.

Storewall

Storewall units are installed.

Desk Install

The desks have been installed.

Desks

The desks have been installed.

Desks

Desks have been installed.

Final Touches

Final clean and mastic to toilets now ready to use!

Manifestation

New manifestation to MD's office.

IT

Client has moved in the IT for staff relocation.

IT

Client has moved in the IT for staff relocations.

Handover

Handover of phase 2 and the 2nd floor.

Handover

Handover of phase 2 and the 2nd floor.

MD Office

MD's office is handed over.

MD Office

MD's office has been handed over.

Reprographics

Reprographics area.

Site Set Up

Ready for the next phase, 1st floor.

Demo

Demo underway in ladies toilet 1st floor.

Site Set Up

Slowly clearing the remainders of 1st floor clutter and setting up temporary lighting.

Partitions

Delivery of partitioning material for 1st floor.

Female Toilets

The opening has been made to extend the first floor female toilets, ready for plastering.

Toilets

The old toilet walls are plastered.

Toilet

Lining out to create the extended part of the toilet is underway.

Crane Lift

Crane lift for the new condensers for first floor AC system.

Reprographics

Lining out to the reprographics area wall.

Extended Toilets

Extended toilet walls are boarded up.

Tea Point

New Tea Point bulkhead and back wall created

Toilets

First fix ductwork to new ladies toilet.

Toilet Wall

Toilet wall lined out to conceal pipework underneath 'floating trough sink'.

Condensers

Out with the old and in with the new!

Data Cabling

Old data cabling being stripped out.

Tea Point

New teapoint extract is first fixed.

New Office

New meeting room and office are created and ready for boarding.

AC

New cassettes and light tiles are located into the ceiling, ready for pipework and connections.

T&J

Tape and jointing underway to new partitions.

Meeting Room

Jointing and first fix electrics in meeting room.

AC

New BC Controller for first floor AC system is installed and being piped up.

Extended Toilet

Jointing to the extended toilet.

Tea Point

First Fix electrics and plumbing installed to tea-point wall.

Plumbing

First fix plumbing to ladies toilet for new sinks.

Chasing

Chasing and first fix AV power in office wall.

Jointed

Reprographics area and comms wall jointed.

Data

First fix new data is underway

Flooring

Floor is plied and screeded in the extended ladies.

Ceiling Grid

New ceiling grid is installed in the ladies.

Tea Point

Tea-Point is delivered ready for install.

AC Pipework

AC pipework is nearly complete internally.

First Fix

First fix data and aerial to new tray in ceiling void.

Jointing

Jointing is complete all ready for decorations to begin.

Lighting

New lighting is on and the new cassettes are installed into the ceiling.

Comms Room

Comms room wall and storage unit.

Decorations

Decorations to basebuild walls are underway!

Glazing

Glazing track is installed.

Glazing

Glazing track is going in!

TPoint

T point has been installed and is protected!

Scaffolding

Scaffolding is going up!

Flooring

Flooring has been tiled and protected.

Ply Being Laid

Ply being laid on the tea-point floor.

Flooring

Floor cleared and tackified ready for carpet.

Carpet

Carpet is being laid.

Latex

Latex screed to tea-point floor.

Carpet

Carpet install is complete.

Vanity Unit

New vanity unit and sink being installed into gents.m

Tea Point

New stone worktop is installed to tea-points.

Worktops

New stone worktop has been installed into the teapoints.

Units

The dark grey matt finish doors are installed to the wall units.

Data

Data install is complete.

Partitions

Glass partitions being installed.

Furniture

Furniture install is well underway.

Plumbing

Plumbing second fix nearly complete in the toilets and mirrors have been installed.

Decorations

Final decorations are being carried out, bragging wall has it its top coat.

Glass Boards

Glass boards and blinds have been installed.

Toilets

New toilet door signage installed.

Furniture

New desking install complete and ready for occupation.

Storewall

Storewall is fitted.

Clock

Artwork to clock wall in tea-point.

Bench Table

Project bench table and stools are installed.

Clipboards

Clipboards are hung on the bragging wall.

Manifestation

Manifestation installed to the office and meeting room.

Toilets

New extended ladies toilets are complete.

Vanity

New vanity unit and trough sink is complete in 1st floor gents.

Furniture

Office furniture has been installed.

Meeting Room

One of the meeting rooms is coming together nicely.

Meeting Room Signage

Meeting room signage is up!

Tea Point

Tea point furniture and pendant lights installed all ready to handover.

Teapoint

Tea Point is complete!

Plasterboard

Plasterboard is delivered for final phase on ground floor.

Lighting

Existing lighting has been removed.

Lighting

Temporary lighting is put up until the new lights are installed.

Data

Old data cabling is stripped out.

Partitions

New partitions are going up.

Meeting Room

New meeting rooms are formed.

New AC

New AC cassettes are delivered to site ready for install.

Meeting Rooms

Meeting rooms and store rooms are all built.

Tea Point

Existing flooring to tea-point is stripped up and ply laid ready for new vinyl.

Tea Point

Existing flooring to tea-point is stripped up and ply laid ready for new vinyl.

Ceiling

The new MF ceiling is installed in the reception.

Meeting Room

Meeting room wall is lined with first fix electrics and AV in place.

TV

The TV recess is created in the reception.

Tea-Point

Tea-Point TV wall lined our ready for OSB.

Partitions

Partitions to create the post room and separate the tea-point.

AC

New AC cassettes are going up.

Ceiling

New MF ceiling being installed in the tea-point.

AC

New AC cassette's and light are in place in the ceiling.

Lighting

Lighting installed in the post room.

Tea Point

Tea-Point MF ceiling and bulkhead is now complete.

OSB

OSB is fitted to the tea point tv wall.

Spot Lights

New spot lights are cut into the reception ceiling.

T&J

T&J to reception TV recess.

T&J

T&J to office.

Site

A view of the site!

Pipework

New pipework being installed for AC system.

Glazing Track

Glazing track and door frames installed.

Decorations

Site progressing and decorations underway.

TeaPoint

Tea point is being installed.

Post Room

Post room storage unit being installed.

Print Area

Print area is being installed.

Tea-Point

Tea-point unit install complete ready for worktop and wall unit doors.

Floating Storage

Floating storage unit in the meeting room.

Partitions

Existing partitioning system is sprayed to freshen it up.

Decorations

Decorations to the new MF ceiling in the tea-point.

Decorations

Decorations are well underway.

Reception

First coat is going in!

TV's

New TVs are fitted to first and second floors.

TV

New TV fitted to 2nd floor tea-point.

AC

The new AC system is gassed up and pressure tested, pipework being labelled.

Lighting

New lighting is cut out in the MF ceiling.

Meeting Rooms

the two new meeting rooms.

Decorations

Decorations to the stairwells are complete and new LED lighting.

Lighting

New lights are on in the tea point!

Tea Point

Tea point is coming along nicely.

Reception

TV wall to reception is decorated.

Entrance

Office entrance hallway is decorated.

Carpet

New carpet is being laid to the main office.

Carpet

Carpet into the new meeting rooms.

Tea Point

Tea-Point floor prepwork done ready for the vinyl!

Glazing

Glazing install to office.

Glazing

Glazing install to meeting rooms.

Vinyl

Vinyl flooring being laid to tea-point.

Doors

Door install complete and digi locks fitted to store room doors.

AC

AC Compound is tidied up with all new condensers now on place.

Stairwell

New carpet and nosing's to stairwell.

Vinyl Flooring

New vinyl flooring complete to reception.

Carpet

New carpet and barrier mat is laid to entrance lobby.

Manifestation

Manifestation is installed onto the meeting rooms.

Storewall

New black storewall is installed.

Signage

Signage to the reception toilet doors.

Desk Lamps

Desk lamps are fitted to the project benches.

Furniture

New furniture installed into the boardroom.

Manifestation

Manifestation, signage and furniture to the interview rooms.

Reception

New reception desk installed with hanging pendants.

Storage Unit

Storage unit and water cooler installed and hanging pendants.

Splashback

Splashback, artwork and special doors fitted to teapoint.

Pendant

Pendant lights have been fitted.

Tea Point

Tea Point at handover.

T Point

Tea point at handover.

T Point

Tea Point at handover.

Handover

Handover day - town hall furniture ready to be moved to the first floor with relocation works,

Print Area

Print area ready for decorations.

Ground Floor

Ground Floor at handover, ready for relocation's.

Office

Office on ground floor at handover.

Storerooms

Storerooms at handover.

Receptions

Reception at handover.

Reception

Reception at handover

Vanity

New vanity units and sink in gents.

Reception

Signage and Artwork

Office

Office at handover.