Matchtech

Matchtech Fareham

Take a look through our project timeline of the Matchtech office in Fareham!

Temporary Partitions

Temporary partitions to separate the 1st and 2nd phase.

Partitions

Temporary partitions to split second floor phase 1 and 2

Partitions

Temporary partitions are up to separate the second floor.

De-Gas

De-gas of existing condensers ready to strip out the first phase AC units.

Partitions

Partition and bulkhead created for new tea-point.

Partitions

Partitions created for Storewall.

Mechanical

Delivery of new AC cassettes and the old ones stripped out.

New Pipework

New pipework is ran for the new AC systems from ground floor compound to first and second floors.

New Pipework

New pipework is ran for the new AC systems from ground floor compound to first and second floors.

T&J

Taping and Jointing new partitions.

BC Box

New BC box installed for the new AC system on 2nd floor.

AC

New AC cassettes have been installed.

LED

New LED light panels being installed into grid.

Data

First fix data is underway.

Tea Point

Tea Point is being installed.

Tea Point

Tea Point is being installed.

Piping

Piping for the first phase AC units is installed from the BC box.

LED Panels

New LED panels are up.

Tea Point

Tea Point is installed, just waiting for the special order wall unit doors and quartz stone worktop.

Decorations

Decorations are underway.

Data

Data second fixed into new cab on 2nd floor, with fibre and copper links to ground floor comms room.

Data

Data second fixed into new cab on 2nd floor, with fibre and copper links to ground floor comms room.

Crane

The crane is here to lift out the old condensers and lift in the new.

AC

The second floor condensers are gone.

AC

New condensers are now in place!

Glazing Track

Black glazing track is installed for glass screen to tea-point and new round lights are installed.

Light

Let there be light!

WC

WC's basin is in!

Flooring

Carpet is down with power and data ready for the desk install.

T-Point

Worktop has been installed.

Desks

Desks have been installed!

Splashback

Splashback has been installed!

Office

First phase is ready to hand over.

TPoint

Tpoint for the first phase is done!

Desks

Desks and furniture are in!

Desks

Desks and furniture is in!

Plastering

Plastering to toilets.

Plastering

Plastering to toilets and new opening.

Partitions

New partitions to extended toilets.

Tea Point

Existing teapoint stripped out.

Partitions

Extended toilet partitions out into the office space.

Pipework

Pipework runs for new AC cassettes.

AC

New AC cassettes and lights going in.

Office

New partitions to create office and meeting room.

Electrics

First fix electrics in partition for TV positions.

Floor

Floor to extended toilet is plied and primed ready for latex screed.