Norwegian Cruise Lines
19
MAR
Before...
The space before we start the works...
19
MAR
Before...
The space before we start the works.
19
MAR
Before...
The space before we start the works..
19
MAR
Before..
Before the works begin...
26
MAR
Carpet
Carpet being lifted and set aside.
26
MAR
Carpet
Carpet being lifted and set aside.
27
MAR
Delivery
Plasterboard has been delivered.
27
MAR
Site Set Up
Site set up is complete!
28
MAR
Tea Point
Tea-point to west wing being created.
29
MAR
Walls
Walls being insulated before being closed.
29
MAR
West Wing
West Wing looking back to main entrance
29
MAR
First Fix
First fix electrics going into walls.
29
MAR
Electrac
New Electrac being installed to sub-floor
03
APR
Delivery
Ductwork delivery.
03
APR
Corner Office
Corner office and meeting room.
04
APR
Partitions
Partitions being closed.
05
APR
Door Frames
New door frames being installed.
06
APR
First Fix
First fix plumbing for new teapoints.
06
APR
First Fix
First fix plumbing for new tea points.
06
APR
Corner Meeting Room
Corner off and meeting room walls closed and frames in.
06
APR
West Wing
A look up the west wing.
06
APR
Walls
Walls closed to training room.
10
APR
Half Height Walls
Half height walls are being constructed.
10
APR
Plumbing
First fix plumbing to tea-point.
11
APR
T&J
Trims fitted ready for Tape & Jointing to start.
11
APR
T&J
Taping & Jointing is underway.
11
APR
Meeting Room
Meeting room is up and almost ready for decorations.
12
APR
T&J
Training room jointing underway.
12
APR
Half Height
Half height walls with first fix electrics
12
APR
AC
First fix access control and AC to comms room.
12
APR
Reception
Reception ceiling tripped ready for MF install.
13
APR
First Fix
First fix ductwork into riser with fire damper.
16
APR
T&J
Tape & Jointing coming along.
16
APR
West Wing
West Wing Tea-Point tape and Jointed
17
APR
Half Height
Half Height Walls are Constructed.
17
APR
East Wing
The east wing is underway
17
APR
East Wing
East wing carpets up and partitions being built.
17
APR
Reception Window
Reception window is formed.
18
APR
Reception
Reception MF ceiling is installed ready for plasterboard.
19
APR
Primer
Primer coat going on walls.
19
APR
Training Room
Training room primer coat.
19
APR
Half Height
Half height wall capping's going on with shadow gap detail.
20
APR
Decorations
Training room decorations are well underway.
20
APR
Decorations
Decorations well underway and skirtings going on.
20
APR
Decorations
Decorations well underway and skirtings on.
20
APR
West Meets East
the wall is down!
23
APR
Ductwork
New ductwork runs up risers and through loft space in roof.
23
APR
Ductwork
New ductwork runs up risers and through loft space in roof.
23
APR
Decorations
Tea-point wall decorated and first fixed ready for unit install.
23
APR
T&J
Tape and Jointing to half height walls in west wing.
24
APR
Data
Data first fix is underway.
24
APR
Data
Data and Decorations in west wing.
24
APR
Ductwork
Ductwork and plant up to roof.
24
APR
Ductwork
Ductwork and plant up to roof
24
APR
Ductwork
Ductwork and plant up to roof.
24
APR
AC
New AC units in comms room.
24
APR
Floorboxes
New floor boxes in place.
25
APR
TPoint
West wing tea point being installed.
25
APR
Half Height Wall
West wing half height walls are decorated.
25
APR
Air Handling Unit
New air handling unit is build in the roof plant area.
25
APR
Ductwork
New ductwork runs with fire dampers are installed from new AHU.
25
APR
West Wing
A view down the west wing.
25
APR
Glazing Track
Glazing track installed in west wing.
25
APR
Decorations
West wing decorations nearly complete.
25
APR
Decorations
Decorations are almost complete in the west wing.
26
APR
AC
New AC pipework is ran through roof space.
26
APR
AC
New AC pipework is ran through roof space.
26
APR
AC
New AC splits for the comms room are located on the rood next to existing units.
26
APR
East Wing
East wing walls are being closed.
27
APR
Folding Wall
Folding wall housing.
27
APR
West Wing
West wing tea-point install coming on.
27
APR
East Wing
East wing tea-point.
27
APR
Reception
Reception MF ceiling is boarded.
27
APR
East Wing
East Wing floating breakfast bar brackets are in and wall closed.
27
APR
East Wing
East wing walls closed and trims being fitted ready for tape and jointing.
27
APR
East Wing
East Wing walls closed and trims being fitted ready for tape and jointing.
27
APR
Data
A lot of data cables pulled already - but more to go yet!
30
APR
T&J
Tape & Jointing to reception ceiling.
30
APR
Reception
Reception tv first fix.
30
APR
Post Room
Post room.
02
MAY
Data
A lot of data cabling is being installed.
03
MAY
Comms Cab
New comms cab have arrived and are built.
03
MAY
Carpet
The carpet is being laid!
03
MAY
Carpet
Carpet is going down and new floor-boxes in!
03
MAY
West Wing
West wing is coming together.
04
MAY
Door Frames
Door frames and glazing track are installed in the east wing ready for glass survey.
04
MAY
East Wing
Tape & Jointing pretty much complete in the east wing.
04
MAY
First Fix
First fix to the boardroom tv.
04
MAY
IRC Room
IRC room jointed and glazing track installed.
04
MAY
Data
Data Cabling to the east wing being installed.
04
MAY
Lighting
Lighting to reception ceiling being cut in.
08
MAY
West Wing
Carpet down the west wing
08
MAY
2nd Fix Electrical
2nd fix sockets being fitted.
09
MAY
Vinyl Flooring
Vinyl flooring being laid in west wing tea-point.
09
MAY
Decorations
Decorations to east wing coming on.
10
MAY
Comms Cab
2nd fix data into the comms cab is well underway
10
MAY
East Wing
Vinyl to east wing tea-point is laid.
11
MAY
Plumbing
2nd fix plumbing underway, water heater being installed.
11
MAY
Doors
Doors are delivered.
11
MAY
Doors
First doors are swinging.
11
MAY
Carpet
Carpet down to the east wing.
11
MAY
Ductwork
Ductwork grills are fitted to the reception plasterboard ceiling.
11
MAY
Data
all 768 data cables are terminated into the new comms cabinet.
11
MAY
Patch Panels
Patch panels all in neatly ready for testing and labelling.
11
MAY
Data
New data cabinets in place ready for clients IT to begin set-up works.
11
MAY
Air Handling Unit
The new air handling unit is all connected up ready to be ran.
11
MAY
Lagging
Lagging is completed to the new ductwork.
14
MAY
Doors
New doors in and ready for glass to be installed.
14
MAY
Glazing
Glazing install is underway.
14
MAY
Glass Install
Glass being installed to individual office.
16
MAY
Glass Doors
Glass doors to west wing tea-point installed.
17
MAY
Glass and Doors
Glass and Doors install nearly complete.
17
MAY
West Wing
A view down the west wing.
17
MAY
Glass Doors
Glass doors to reception and carpet all installed.
17
MAY
IRC Room
Carpet and glass installed to east wing - IRC Room
17
MAY
Carpet
Carpet install complete in east wing.
17
MAY
Carpet
Carpet down and IT workbench is installed.
18
MAY
Boardroom
The main boardroom is all carpeted and ready for the folding wall insert.
18
MAY
IT
Patching is underway by the client's IT
18
MAY
Blinds
Blinds are installed
21
MAY
Lighting
Lighting installed to reception ceiling following decorations.
22
MAY
Reception Desk
New reception desk has been installed.
22
MAY
Folding Wall
Folding wall panels have been installed.
22
MAY
Splashback
The glass splashback has been installed.
23
MAY
Manifestation
Manifestation is going onto the new glazing.
23
MAY
Splashback
Glass splashback is in and the coffee machine has been installed in the east wing.
23
MAY
Desks
New desks have been installed.
23
MAY
Joinery
Joinery ceiling raft has been fitted.
23
MAY
Pendant Lights
Pendant Lights fitted in the tea-point.
24
MAY
Manifestation
Manifestation to glass doors to west wing t-point.
24
MAY
Lights
Lights installed and manifestation onto the reception seating area. m
24
MAY
Reception
Reception is almost complete!
25
MAY
Comms Cab
Patching to the new comms cabs is nearly complete.
25
MAY
Desks & Signage
New desks and signage all installed to finance area.
25
MAY
Signage
New signage to office work areas.
25
MAY
Reception
A view down reception area.
25
MAY
Signage
New signage and manifestation to boardroom.
25
MAY
Post Room
The post room is complete and ready to go!
25
MAY
Branding
Branding to east wing entrance.
25
APR
Banquette Seating
Banquette seating to west wing tea-point.
25
MAY
AV
Reception AV is installed.
29
MAY
Projector
Relocated projector with new screen.
29
MAY
Handover
Reception at Handover
29
MAY
TeaPoint
T-Point at handover.
29
MAY
IRC Room
IRC Room at handover.