Norwegian Cruise Lines

Before...

The space before we start the works...

Before...

The space before we start the works.

Before...

The space before we start the works..

Before..

Before the works begin...

Carpet

Carpet being lifted and set aside.

Carpet

Carpet being lifted and set aside.

Delivery

Plasterboard has been delivered.

Site Set Up

Site set up is complete!

Tea Point

Tea-point to west wing being created.

Walls

Walls being insulated before being closed.

West Wing

West Wing looking back to main entrance

First Fix

First fix electrics going into walls.

Electrac

New Electrac being installed to sub-floor

Delivery

Ductwork delivery.

Corner Office

Corner office and meeting room.

Partitions

Partitions being closed.

Door Frames

New door frames being installed.

First Fix

First fix plumbing for new teapoints.

First Fix

First fix plumbing for new tea points.

Corner Meeting Room

Corner off and meeting room walls closed and frames in.

West Wing

A look up the west wing.

Walls

Walls closed to training room.

Half Height Walls

Half height walls are being constructed.

Plumbing

First fix plumbing to tea-point.

T&J

Trims fitted ready for Tape & Jointing to start.

T&J

Taping & Jointing is underway.

Meeting Room

Meeting room is up and almost ready for decorations.

T&J

Training room jointing underway.

Half Height

Half height walls with first fix electrics

AC

First fix access control and AC to comms room.

Reception

Reception ceiling tripped ready for MF install.

First Fix

First fix ductwork into riser with fire damper.

T&J

Tape & Jointing coming along.

West Wing

West Wing Tea-Point tape and Jointed

Half Height

Half Height Walls are Constructed.

East Wing

The east wing is underway

East Wing

East wing carpets up and partitions being built.

Reception Window

Reception window is formed.

Reception

Reception MF ceiling is installed ready for plasterboard.

Primer

Primer coat going on walls.

Training Room

Training room primer coat.

Half Height

Half height wall capping's going on with shadow gap detail.

Decorations

Training room decorations are well underway.

Decorations

Decorations well underway and skirtings going on.

Decorations

Decorations well underway and skirtings on.

West Meets East

the wall is down!

Ductwork

New ductwork runs up risers and through loft space in roof.

Ductwork

New ductwork runs up risers and through loft space in roof.

Decorations

Tea-point wall decorated and first fixed ready for unit install.

T&J

Tape and Jointing to half height walls in west wing.

Data

Data first fix is underway.

Data

Data and Decorations in west wing.

Ductwork

Ductwork and plant up to roof.

Ductwork

Ductwork and plant up to roof

Ductwork

Ductwork and plant up to roof.

AC

New AC units in comms room.

Floorboxes

New floor boxes in place.

TPoint

West wing tea point being installed.

Half Height Wall

West wing half height walls are decorated.

Air Handling Unit

New air handling unit is build in the roof plant area.

Ductwork

New ductwork runs with fire dampers are installed from new AHU.

West Wing

A view down the west wing.

Glazing Track

Glazing track installed in west wing.

Decorations

West wing decorations nearly complete.

Decorations

Decorations are almost complete in the west wing.

AC

New AC pipework is ran through roof space.

AC

New AC pipework is ran through roof space.

AC

New AC splits for the comms room are located on the rood next to existing units.

East Wing

East wing walls are being closed.

Folding Wall

Folding wall housing.

West Wing

West wing tea-point install coming on.

East Wing

East wing tea-point.

Reception

Reception MF ceiling is boarded.

East Wing

East Wing floating breakfast bar brackets are in and wall closed.

East Wing

East wing walls closed and trims being fitted ready for tape and jointing.

East Wing

East Wing walls closed and trims being fitted ready for tape and jointing.

Data

A lot of data cables pulled already - but more to go yet!

T&J

Tape & Jointing to reception ceiling.

Reception

Reception tv first fix.

Post Room

Post room.

Data

A lot of data cabling is being installed.

Comms Cab

New comms cab have arrived and are built.

Carpet

The carpet is being laid!

Carpet

Carpet is going down and new floor-boxes in!

West Wing

West wing is coming together.

Door Frames

Door frames and glazing track are installed in the east wing ready for glass survey.

East Wing

Tape & Jointing pretty much complete in the east wing.

First Fix

First fix to the boardroom tv.

IRC Room

IRC room jointed and glazing track installed.

Data

Data Cabling to the east wing being installed.

Lighting

Lighting to reception ceiling being cut in.

West Wing

Carpet down the west wing

2nd Fix Electrical

2nd fix sockets being fitted.

Vinyl Flooring

Vinyl flooring being laid in west wing tea-point.

Decorations

Decorations to east wing coming on.

Comms Cab

2nd fix data into the comms cab is well underway

East Wing

Vinyl to east wing tea-point is laid.

Plumbing

2nd fix plumbing underway, water heater being installed.

Doors

Doors are delivered.

Doors

First doors are swinging.

Carpet

Carpet down to the east wing.

Ductwork

Ductwork grills are fitted to the reception plasterboard ceiling.

Data

all 768 data cables are terminated into the new comms cabinet.

Patch Panels

Patch panels all in neatly ready for testing and labelling.

Data

New data cabinets in place ready for clients IT to begin set-up works.

Air Handling Unit

The new air handling unit is all connected up ready to be ran.

Lagging

Lagging is completed to the new ductwork.

Doors

New doors in and ready for glass to be installed.

Glazing

Glazing install is underway.

Glass Install

Glass being installed to individual office.

Glass Doors

Glass doors to west wing tea-point installed.

Glass and Doors

Glass and Doors install nearly complete.

West Wing

A view down the west wing.

Glass Doors

Glass doors to reception and carpet all installed.

IRC Room

Carpet and glass installed to east wing - IRC Room

Carpet

Carpet install complete in east wing.

Carpet

Carpet down and IT workbench is installed.

Boardroom

The main boardroom is all carpeted and ready for the folding wall insert.

IT

Patching is underway by the client's IT

Blinds

Blinds are installed

Lighting

Lighting installed to reception ceiling following decorations.

Reception Desk

New reception desk has been installed.

Folding Wall

Folding wall panels have been installed.

Splashback

The glass splashback has been installed.

Manifestation

Manifestation is going onto the new glazing.

Splashback

Glass splashback is in and the coffee machine has been installed in the east wing.

Desks

New desks have been installed.

Joinery

Joinery ceiling raft has been fitted.

Pendant Lights

Pendant Lights fitted in the tea-point.

Manifestation

Manifestation to glass doors to west wing t-point.

Lights

Lights installed and manifestation onto the reception seating area. m

Reception

Reception is almost complete!

Comms Cab

Patching to the new comms cabs is nearly complete.

Desks & Signage

New desks and signage all installed to finance area.

Signage

New signage to office work areas.

Reception

A view down reception area.

Signage

New signage and manifestation to boardroom.

Post Room

The post room is complete and ready to go!

Branding

Branding to east wing entrance.

Banquette Seating

Banquette seating to west wing tea-point.

AV

Reception AV is installed.

Projector

Relocated projector with new screen.

Handover

Reception at Handover

TeaPoint

T-Point at handover.

IRC Room

IRC Room at handover.