Top Secret London Project
10
JUN
Top Secret Client
Take a look through our North London client's exciting new project!
11
JUN
CAT A
CAT A works are finishing up, ready for Space to start.
12
JUN
Power & Data
Containment in ceiling for power and data.
13
JUN
Chasing Out
Chasing out works are ongoing for floor containment.
14
JUN
Access Control
First fix access control
15
JUN
Tea Point
The first fix plumbing for the tea point.
15
JUN
Partitions
The metal studs for the partitions are erect!
16
JUN
Comms Room
The comms room partition is erect.
16
JUN
Partitions
Insulation and ply installed to partitions.
19
JUN
Flooring
The floor is being prepared for the tea point.
20
JUN
Power & Data
Power & Data are being installed.
20
JUN
Tea Point
The shape of the tea point is in place, as well as the power ready for the full install!
22
JUN
Concrete
Laying concrete base to level out trunking.
23
JUN
Sockets
Sockets are being installed.
23
JUN
Skirting
Skirting trunking installed.
23
JUN
T&J
Taping & Jointing is underway.
26
JUN
Tea Point
Tea point is being installed.
26
JUN
T&J
Tape & Jointing is underway in the recessed wall for the TV
27
JUN
Wall Track
Folding wall track installed.
27
JUN
Wall Coverings
Brick wall coverings are up!
28
JUN
Door Frame
The door frame is being installed.
Post navigation
<
>