Constructor Group

12SEP
Constructor Group
The front of the existing warehouse, with Space just about to get started and stuck in!








19SEP
Ceiling
First floor ceiling removed - time to begin carefully removing the cabling mess left behind.









24SEP
Asbestos Works
Main entrance area sealed for the duration of the asbestos works to keep everyone safe.



26SEP
Drainage Connection
Front trench is filled back in with drainage connections ready to be ran into building in new locations and temporary water feed lagged.


26SEP
Taking apart
Mezzanine floor cleared ready for the old water tank to be removed and then the whole floor itself can be taken apart.






02OCT
Asbestos safely removed
Main corridor also returned to bare concrete and all asbestos safely removed.
































23NOV
Pad Stones Ready For Mezzanine
New pad stones are in all ready for the Mezzanine to be installed.



28NOV
Insulation
Insulation is nearly complete to the front elevation covering all beams and purlins.

06DEC
Mezz
Mezzanine floor is being installed this photo shows the main steel beams and the joists that will hold up the floor.






08DEC
Roller Shutter
Roller shutter fully installed over the weekend, looking nice in the goosewing grey, a definite improvement on the old one!




















































21JAN
Liquid DPM
Liquid DPM is applied to the floor in the corridor and tea point to prep it for flooring.



























05FEB
Ground Floor
Ground floor cleared and prepped ready for T.Vs to be installed in meeting rooms.















































