Hywin Wealth
04
JUL
Carpet
Carpet all up ready for ceiling works
04
JUL
Site Office
Temporary site office and welfare area.
04
JUL
Delivery
Clearing space ready for the plasterboard delivery!
04
JUL
Site Ready
Getting site ready, site signage and carpet protection
17
JUL
Ceiling
Open ceiling up for new folding wall track.
7/
JUL
T-point
Ply and 1st fix plumbing to back of t-point area.
7/
JUL
T-point
T-point walls all up.
7/
JUL
Stud work
Stud work for Coms room, repro area and CEO office.
12
JUL
Bulkhead
High level bulkhead for pipe work.
12
JUL
Boards
Boards going on for Coms room, repro area and CEO office.
12
JUL
Toilets
AC unit removed, toilet walls all up.
12
JUL
T-point
High level units up in the t-point and waste and water pipe work 1st fixed.
14
JUL
Bulk Head
Bulk head for pipe work ready to be tape and jointed
14
JUL
Door Frames
Door Frames to the toilets are erect.
14
JUL
TPoint
Tpoint all installed just waiting on glass splash back.
14
JUL
Door Frames
Door frames into meeting rooms.
17
JUL
Bulk Head
Bulk head, tape and jointed under way
17
JUL
Door Frame
Door frame to CEO office and tape and jointing
17
JUL
Comms Cabinet
Comms cabinet
24
JUL
Carpet
Carpet down in CEO office and glazing track all in.
24
JUL
Ply
Ply down in the TPoint and toilets
24
JUL
Ceiling
Ceiling all patched in and tape and jointed ready for folding wall panels.
24
JUL
TV's
Wall units in for tv's in meeting rooms!
24
JUL
Flooring
Carpet down towards the main door.
25
JUL
Toilets
New flooring in the toilets
25
JUL
Meeting Rooms
All relocated lights on in the meeting rooms!
28
JUL
Meeting Rooms
Meeting room doors and glazing!
31
JUL
Storage
Furniture is going into the meeting rooms.
01
AUG
Tea Point
Tea Point has been installed!
02
AUG
Meeting Room
Meeting room doors and new carpet is installed.
02
AUG
Flooring
Toilet doors and new flooring has been installed!
02
AUG
Breakfast Bar
Breakfast bar and pendant lights!
02
AUG
Flooring
Flooring in the tea point.
04
AUG
Open Plan
Open plan area - the new carpet has been laid.
04
AUG
CEO Office
Manifestation has been installed onto the CEO office.
04
AUG
Reprographics Area
Reprographics area has has the high level units installed.
04
AUG
Toilets
Male toilets are all finished.
04
AUG
TPoint
T-point and breakfast bar are finished.
04
AUG
Meeting Rooms
Meeting rooms and manifestation looking good!
04
AUG
Folding Wall
A folding wall has been put into the meeting rooms to allow extension for larger meetings.