Top Secret Client
20
MAY
Site Set Up
Site set up
21
MAY
Partitions
Partitions & and ply in walls starting to be installed.
23
MAY
Partitions
More partitions going up
24
MAY
Curved Feature Corridor
Curved feature corridor taking shape.
28
MAY
Boardroom
Boardroom starting to take shape
29
MAY
Data
Data being 1st fixed within the floor void.
29
MAY
AC Units
New A/C units being installed
30
MAY
Small Power
Small Power & Data 1st fixed
30
MAY
Small Power
Small power and Data now within partitions
30
MAY
HR Office
HR office taking shape.
31
MAY
Boardroom
Boardroom small power 1st fixed and door frames going in
31
MAY
Plumbing
1st fix plumbing
03
JUN
Tape And Jointing.
Tape & Jointing new partitions have begun.
04
JUN
Tape And Jointing
Tape & Jointing progressing well.
04
JUN
Door Frames
Door frames being installed
04
JUN
Folding Walls
Folding wall head track installed.
05
JUN
Skirting
Skirting being installed
07
JUN
Doors
Doors being installed.
10
JUN
T-Point
Tea point ceiling installed and tape & jointed.
11
JUN
New Partitions
Decorating moving forward, 1st coat of paint on the new partitions.
11
JUN
Acoustic Barrier
Acoustic barrier being installed to ceiling void.
12
JUN
Ready For Approval
Tea Point being installed & feature colour samples on ready for approval.
13
JUN
Feature Colours
Feature colours now going on walls.
14
JUN
T-Point Install
Tea Point Installed.
17
JUN
Decorations
Final decorations going on.
17
JUN
Storage
Storage units installed.
17
JUN
Data
Data being 2nd fixed into cabinet.
18
JUN
Boardroom Complete
Carpet being installed, Boardroom complete.
18
JUN
Meeting Rooms
Carpet to meeting rooms installed.
18
JUN
T-Point
Prep work to the floor in the Tea Point.
19
JUN
Comms Cab
Comms cab installed and completed.
20
JUN
T-Point Flooring
Tea Point flooring installed and protected.
21
JUN
Glazing
Glazing Installed.
24
JUN
Store Wall
Store wall installed.
25
JUN
Lockers
Lockers installed.
25
JUN
Desk Installed
Sit/Stand Desks installed.
26
JUN
Boardroom
Boardroom folding wall installed
27
JUN
Acoustic Rafts
Acoustic rafts installed
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!
09
JUL
Handover
The new office is complete!