ESET
06
NOV
ESET
Take a look through the timeline to see how our project over at ESET is coming along!
06
NOV
Site Set Up
Site set up is complete!
06
NOV
Strip Out
Strip out of existing carpet tiles, ceiling tiles & wallpaper.
07
NOV
Toilets
Existing Toilets are stripped out!
08
NOV
Toilets
Existing toilets ceiling has been stripped out.
09
NOV
First Fix Plumbing
First Fix plumbing works in.
09
NOV
Comms Room
New Comms room floor has been installed.
10
NOV
AC
AC containment being installed.
13
NOV
Chasing
Chasing into walls complete for TV power, data and AV.
14
NOV
Making Good
Making good to wall where existing carpet was.
15
NOV
AC
A/C services and contained data cables being pulled through lobby ceilings.
15
NOV
Partitions
First lot of partitions are being installed.
16
NOV
Electrical
First fix electrical into new partitions.
17
NOV
AC
A/C cassettes are now starting to be installed.
20
NOV
Partitions
Partitions are going up!
21
NOV
Power & Data
Power, Data & AV going into the walls for TV's etc.
24
NOV
Flooring
Preparation to flooring in toilets.
22
NOV
T&J
Taping and jointing has begun to the new partition walls.
23
NOV
Tea Point
Tea point 1 ready for install.
23
NOV
Tea Point
Tea point 2 ready for install.
23
NOV
Ply
Ply on floor in preparation for vinyl flooring install.
24
NOV
Plumbing
1st fix plumbing to tea points and toilets complete.
25
NOV
AC
Crane lift to install new A/C condensers onto roof.
27
NOV
Glazing Track
Glazing track and door frames installed.
28
NOV
Tea Point
Tea Point 1 has been installed.
29
NOV
Coffee Station
Coffee station has been installed!
30
NOV
Carpet
Carpet is being laid.
30
NOV
Toilet Lighting
Toilet lighting is being installed.
01
DEC
Doors
Doors are being installed.
01
DEC
Comms Room
Comms room door installed.
02
DEC
Comms Room
Comms rooms is almost complete!
05
DEC
Furniture
Furniture has been installed!
07
DEC
Coffee Point
The coffee point furniture is installed.
11
DEC
Training Room
Training room TV has been installed as well as all of the furniture.
11
DEC
Signage
Signage is installed!
12
DEC
Reception
All the signage and desks are installed for the reception area.
12
DEC
Blinds
Blinds have been installed!
13
DEC
Gifts
Gifts for the desks have arrived!
13
DEC
Manifestation
Manifestation has been installed.
14
DEC
T-Point
Tea point furniture has been installed.
15
DEC
Colour
Love that blue!
15
DEC
Breakout Area
Breakout area is kitted out with some fab furniture!
15
DEC
TPoint
Breakout area t point is complete!
16
DEC
Toilets
Toilets are complete!