Moneybarn

Ground Floor

Existing Ground Floor

Ground Floor

Existing ground floor walls.

Ground Floor

Existing ground floor.

Ground Floor

Existing ground floor before works begin.

Existing Ground Floor

Different angles of the ground floor before works.

Existing Ground Floor

Different angles of the ground floor before works.

Existing First Floor

Before the works commence on the first floor.

Existing Ground Floor

Window view on first floor.

First Floor

Existing first floor.

First Floor

Existing offices on the first floor.

Front Entrance

Front entrance to the building which will become the back entrance.

Site Set Up

Site set up being delivered.

Site Set Up

Site set up, ready for works to begin.

Site Set Up

Site set up, ready for it to begin.

First Floor

First floor being stripped out

Strip Out

First floor strip out.

First Floor

Strip out being completed on first floor ready for works.

Strip Out

First Floor being completely stripped out.

Wire Strip Out

Wires in the ceiling are being stripped out.

Outside Works

Works commencing outside.

Metal Strip Out

Metal completely stripped from ceilings.

Scaffolding

Scaffolding being evicted.

Scaffolding

Scaffolding being evicted

Digger

Delivery of plant hire.

Installment Of Netting

Demo installed safety netting.

Installment Of Netting

Demo installed safety netting.

Safety Netting

Safety netting installed.

Roof Materials

Arrival of roofing materials

Roofing Materials

Roofing materials being lifted into place

Roofing Materials

Roofing materials being lifted into place.

Roof Panels

Roof panels being removed

Roof Panels

Roof panels being removed.

Installment

Roof materials being installed

External Decorations

External decorations have started.

Window Films

Ground floor window films are removed to allow more natural light in.

Safety Netting

Safety netting removed from first floor

Netting

Netting removed from the back of the 1st

Ceiling Cleared

Ceiling cleared at back of ground floor.

Ceiling Cleared

Ceiling cleared at back of ground floor.

Ceiling Cleared

Ceiling cleared at back of ground floor.

Snagging

First floor ceiling snagging begins.

Demo

Second half of ground floor prepped for demo

Ground Floor

Ground floor central wall begins to be removed.

Ground Floor

Ground floor half cleared.

Gutters

Re-lining the existing gutters.

Roofing Panels

Roofing panels fully fitted including the hips.

Old Vaults Cleared

Old vaults cleared of lights and containment.

Old Toilets

Tiles removed from walls in old toilets.

Snagging

Snagging begins on ground floor.

Roof Removed

Old entrance porch glass and roof removed.

Lift Shaft - First Floor

Lift shaft removed on 1st and ground floor.

Demolition

Demolition nearly completed

Demolition

Demolition nearly completed

Demolition

Demolition nearly completed

Demolition

Demolition nearly completed

Demolition

Demolition nearly completed

Demolition

Demolition nearly completed

New Drainage Runs

Concrete cut out to install new drainage runs.

Drainage Works

Drainage works Continue.

Drainage Works

Drainage works Continue.

Insulation Works

Insulation works to stop the cold bridging.

1st Floor

Insulation to stop cold bridging nearly completed on 1st floor.

New Drainage

New drainage pipes begin to be installed.

New Drainage

New drainage pipes begin to be installed.

New Doorways

New doorways and lintels installed.

Removed Front Porch

Front porch fully removed.

Drainage Runs Installed

New drainage runs installed in.

Drainage Runs Installed

New drainage runs installed in.

Door Openings

All door opening lintels have been put in place.

Rubble Removed

More rubble removed from the first floor openings

Drainage

Drainage is completely back filled and prepped for concrete.

Containment Opening

Containment opening made in wall for services to pass.

Plasterboard

Fixings for plaster board are screwed in ready for lining out

Ground Floor Columns

Ground floor columns are fire lined.

First Floor

More containment and ducting installed on the first floor

Final Doorway

Final doorway is infilled to create the new layout.

Drainage

Drainage is all completely backfilled and prepped for concrete

Windows

Window openings.

Ductwork

Duckwork first fix.

Ductwork

Ductwork first fix

Windows

Internal window openings

Internal Windows

Internal window openings

Raised Access Flooring

Raised Access flooring being fitted

Raised Access Flooring

Raised access flooring being fitted.

Raised Access Flooring

Raised access flooring being fitted.

Flooring Upstairs

A quarter of the floor is placed upstairs.

AC - Ground Floor

AC duct on the ground floor is nearly fully lagged.

Floor Tiles

Floor tiles are ready to be placed on the first floor.

Plumbing Installation

Plumbing installation in ground floor toilets.

Scaffolding Removed

Outside of the building with the scaffolding removed.